The project being coordinated by Nancy Kanyango includes modern multi-storeyed buildings to host High Courts in Mombasa, Kakamega, Siaya, Nakuru, Voi and Garissa.

Corruption and procurement irregularities have caused delays in completion of the construction of Sh10.5 billion courts project.
This has forced the Judiciary seek for an extension of time from the World Bank for the project expected to be complete in December.
The five year project funded by the bank under the Judicial Performance Improvement Programme (JPIP) through a loan that is to mature within 40 years with a grace period of 10 years is aimed at constructing 30 courts (10 High Court and 20 magistrates) in a bid to bring services closer to the people.
The project being coordinated by Nancy Kanyango includes modern multi-storeyed buildings to host High Courts in Mombasa, Kakamega, Siaya, Nakuru, Voi and Garissa. “It is true the Judiciary has written to the World Bank through the Treasury for a two year extension,” said JPIP’s Communication Director Nicholas Simani.
Of the 30 sites, contractors are yet to begin work in Kapsabet and Kajiado.
World Bank website
Rehabilitation works under the supervision of the Judiciary Directorate of Building Services (BDS) are also to be completed in Molo, Makindu, Maralal, Muhoroni, Nyamira, Nyando, Oyugis, Kapsabet, Kibera, Kapenguria and Isiolo.
According to reports on the World Bank website, implementation of Phase 2 of the Kangema Law Courts was delayed in 2015 due to allegations of corruption in the tendering process. It was alleged that some staffers solicited unlawful payments from the winning bidder in exchange for receiving their ‘lost’ bid documents. The Judiciary notified the bank and referred the matter to the Ethics and Anti-Corruption Commission for action.
This saw the bank implement measures to prevent future ‘loss’ of documents by ensuring multiple copies and e-copies were filed in the system.
In a report by the Auditor General for the year ended June 30, 2017, lengthy procurement process that led to delays in awarding of tenders was listed as one of the major challenges the project faced. IFMIS failure, court cases touching on the land where some of the projects were to take place, security and inadequate capacity by implementing units especially on planning, budgeting and reporting have also been blamed for the delays in implementation of some of the constructions.
During that financial year, 28 construction projects had been awarded through the tendering process and eight of them had not started by then.
Chief Justice David Maraga and his team have been traversing the country to commission pending construction works in various regions.
Justice Maraga last week commissioned the construction of court buildings in Mombasa, Siaya, Kakamega and Voi.
“The Judiciary is looking to construct new courts in each county to reduce the costs incurred by litigants from far flung areas traveling to attend courts,” said the CJ when he commissioned the construction of the Sh445 million Justice Tower in Mombasa.
~ Standard Media Group
more recommended stories
MZIMA II WATER PROJECT: KSh 50.6 BILLION COASTAL PIPELINE MOVES CLOSER TO IMPLEMENTATIONChinese firm identified as proposed developer.
Nairobi in Darkness as Government Billing Dispute Leaves Residents Paying the PriceNAIROBI — As darkness descends on.
RUTO CONTRADICTS HIMSELF ON FOREIGNERS: FROM “VISA-FREE AFRICA” TO A CRACKDOWN ON SMALL TRADERSPresident William Ruto’s latest crackdown.
NEW UNIFORMS, SAME OLD PROBLEMS: YOU CAN’T TAILOR INTEGRITYPresident William Ruto has proudly unveiled.
SHARON’S JUSTICE CANNOT BE BOUGHTThe latest developments in the.
HOMA BAY VIOLENCE RAISES TROUBLING QUESTIONS ABOUT KENYA’S DEMOCRACYThe shocking violence that engulfed the.
JUSTICE AT LAST: WHAT THE SHARON OTIENO MURDER CONVICTION MEANS FOR KENYAAfter nearly eight years of.
ALBERT OJWANG CASE: THE QUESTIONS KENYA REFUSES TO LET DIEThe death of Albert Ojwang in.
RELIEF FOOD SCANDAL RAISES SERIOUS QUESTIONS AS INVESTIGATIONS CONTINUEThe reported recovery of hundreds.
THE HALIMA NGACHE CASE: A COSTLY ASSAULT ON DIGITAL FREEDOM THAT DEMANDS ACCOUNTABILITYThe collapse of the case against.
WHY FIKIRINI JACOBS MUST STEP ASIDE AS THE CECIL OUMA PROBE CONTINUESThe tragic death of 28-year-old youth.
STOP THE KILLING, NOT MERELY COMPENSATE THE DEADAs Kenya approaches the second.
PRESIDENT RUTO’S FREQUENT FLYER PRESIDENCY: ARE KENYANS GETTING VALUE FOR MONEY?President William Ruto has returned to.
THE SINGAPORE ILLUSION: A REALITY CHECK ON THE STATE OF OUR NATIONThere is an increasingly persistent.
Could the Proposed Ebola Quarantine Facility Cost Kenya More Than It Gains?The proposed establishment of a United.
RUTO’S HAMMER POLITICS: WHY KENYA CANNOT BE GOVERNED THROUGH ENDLESS PUBLICITY TOURS“If your only tool is.

Leave a Comment