Started in October last year and the completion date supposed to be April 2021, Chengoni Bridge in Kilifi South was supposed to be a saviour to the residents of Kaloleni and Mwaarakaya.
However, for now there is only wood and few pieces of timber laid across the river, and there is no activity ongoing four months to the completion date.
The bridge is supposed to cost Ksh55 million funded by the government through the Equalisation Fund.
On Monday, November 9, a team from the Special Funds Accounts committee visited the site only to find a ghosted site, where only Ksh5.5 million has been spent on construction so far.
“The construction of this bridge started in October last year and the completion date is supposed to be April 2021. We are four months to the completion date and he (contractor) has done up to 24 per cent,” said Committee chairman Murungi Kathuri.
When the team visited, the contractor was not on site, despite being informed of the visitation, indicating that there is no hope of even completing the work.
“There is no work going on at the site at the moment and the contractor is not even around despite sending him a communication that we will be visiting today,” added Kathuri.
According to a “site engineer” who was on site, the contractor was attending “other duties”, and the company had applied for extension of construction period by two months.
“We have applied for extension of the completion period with two months so by June the bridge will be complete,” he said.
Nyandarua Woman Representative Faith Wairimu noted that the site had been abandoned and there was no promise that the contractor would complete the job even with the extended time.
“Grass has grown where you store your wheelbarrows, a clear demonstration that they are not being used. We have not seen even a single person working here. How can we tell this is an active site?” posed Wairimu.
Even as the rainy season approaches, the river could claim more lives and it might take another contractor to complete the project.
more recommended stories
THE GOVERNOR DISCOVERS FISCAL DISCIPLINE — FOUR YEARS TOO LATE?Perhaps one of the most.
SHAKAHOLA: 200 YEARS FOR MACKENZIE, BUT WHO WILL ANSWER FOR THE STATE’S FAILURE?Kwaela News Network | Editorial.
WHO IS THIS GOVERNOR TAITA-TAVETA COUNTY IS LOOKING FOR BEYOND 2027?As the 2027 General Election.
COURT HALTS COAST WATER DISCONNECTIONS AS EJF CHALLENGES SH6 BILLION DEBT CLAIMKwale, 29 August 2026 —.
THE LEGENDARY 70-YEAR-OLD MZIMA PIPELINE LIVES TO BURST ANOTHER DAYGovernment Celebrates Repairing What It Failed.
TRAGIC LOSS OF JOHN KALAGHE JOSHUA LEAVES FAMILY AND COMMUNITY IN MOURNINGIt is with profound sorrow and.
THE NAIROBI–MOMBASA EXPRESSWAY: A DECADE OF PROMISES, YET NO HIGHWAY IN SIGHTThe Highway That Exists Only.
FROM FUEL TO DRINKING WATER: HOW A BILLION-SHILLING PIPELINE DREAM RAN AGROUNDA Lesson in Why Politics Should.
LIKONI BRIDGE: WHAT HAPPENED TO RUTO’S KSH 100 BILLION PROMISE?For years, residents of Mombasa and.
MZIMA PHASE TWO: SIX DECADES OF PROMISES, DELAYS AND GOVERNMENT FAILURECoast Residents Continue to Suffer as.
ABSENT LEADERSHIP OR CALCULATED DISRESPECT? QUESTIONS MOUNT OVER KINGI’S NO-SHOW AT MGANGE NYIKA FUNDRAISER.Serious questions are emerging following the.
ATHANAS MBELE’S “BIG 7 AGENDA” VISION POSITIONS WUNDANYI FOR TRANSFORMATIONAL GROWTHWundanyi is emerging at the center.
POLITICS ON OVERDRIVEKenya is not a permanent.
WHY TAITA TAVETA NEEDS ITS OWN POLITICAL VEHICLEBy Geoffrey Kimonge (GK) The Case.
HAS GREED CONSUMED THE TAITA TAVETA COUNTY ASSEMBLY?By Geoffrey Kimonge (GK) Has the.
THE COLLAPSE OF PAA: AMASON KINGI’S POLITICAL HOLLOWING EXPOSED IN MAGARINI AND TAITA TAVETABy any political measure, Pamoja.

Leave a Comment