In December, the Sh1.9 billion floating bridge linking Mombasa Island and the South Coast through Likoni will be complete, according to the implementing agencies.
This will be the first of infrastructure projects expected to alter the face of Mombasa and propel it to a modern city status.
Currently, the projects whose total cost is put at over Sh116.3 billion by government officials are on scheduled. Most of the projects, will be complete in five years.
On Thursday, President Uhuru Kenyatta said the 660-metre pedestrian floating bridge will reduce congestion at the Likoni ferry terminus currently serving 350,000 passengers per day.
“The Likoni bridge between Liwatoni and Likoni will also help de-congest the ferries and ease pedestrian connection,” President Kenyatta told parliament.
The bridge a first of its kind in the region, will comprise a 529m long floating section, and 54m long approaches on either side of the floating span.
It will complement the existing ferry services to streamline ‘safe passageways’ for pedestrians and reduce overcrowding.
Meanwhile, Mombasa County has also set up recreation activities within the island with the rehabilitation of the old Railway roundabout almost complete.
Last year, Mombasa County and National Government also completed the rehabilitation of the Mama Ngina Waterfront at a cost of Sh460 million.
Yesterday Kenya National Highway Authority (KeNHA) officials said the construction of the Sh28 billion Dongo Kundu bypass was at an advanced stage.
Samuel Ogege KeNHA Deputy Director-General added that construction of the Sh60 billion Mombasa Gateway Bridge across the Likoni ferry channel will start in April next year.
The bridge designs are similar to Golden Gate Bridge connecting San Francisco, California and San Francisco Peninsula in the US.
Golden Gate Bridge is one of the most photographed bridges in the world because of its beauty and unmatched architectural designs.
Engineer Ogege said the construction of the Mombasa Gateway Bridge will start in April next year and completed in early 2025.
Construction of phase two of the Dongo Kundu bypass project which comprises of Mteza and Mwache bridges is 15 per cent done, according to the engineer.
The phase comprises of laying of the 1,440 metres of Mteza bridge, 690 metres viaduct and 660 metres of Mwache bridge.
It is being developed at a cost of Sh22 billion. Sh2 billion will go towards compensating about 300 families who have been moved to pave way for the bridge’s construction.
“This phase (two) started early this year, most of the piling materials that will be used on the by pass such as pipes have arrived in the country. It will take four years for the entire job to be done,” said Ogege.
Phase three of the bypass consists of a 7 km road from Mteza to Kibundani which is is 70 per cent complete and will be ready by March next year.
The road which connects the Likoni-Lunga Lunga highway at Ng’ombeni area will also link to the Dongo Kundu special economic zone.
Meanwhile, KeNHA and Kenya Airports Authority will in the next two weeks embark on Sh600 million correctional works on the phase one of the Dongo Kundu project which was completed in 2018.
Ogege explained that the works will involve directing storm water from the Moi International Airport to the sea to stop possible land slides that can affect the Miritini-Kipevu road, the airport and the Standard Gauge Railway (SGR) line.
“The construction of the six-lane dual carriage Mombasa-Jomvu road that started in 2016 is at 79 per cent complete,” added Charles Njogu on the Authority’s achievements in the port city.
Njogu the KeNHA Assistant Director of communication said the section will cost Sh8.9 billion. It is part of the 32 kilometer Mombasa-Jomvu-Mariakani road project.
Other projects are Mombasa-Mtwapa-Kilifi dual carriage highway to be funded by Africa Development Bank (AfDB).
more recommended stories
THE GOVERNOR DISCOVERS FISCAL DISCIPLINE — FOUR YEARS TOO LATE?Perhaps one of the most.
SHAKAHOLA: 200 YEARS FOR MACKENZIE, BUT WHO WILL ANSWER FOR THE STATE’S FAILURE?Kwaela News Network | Editorial.
WHO IS THIS GOVERNOR TAITA-TAVETA COUNTY IS LOOKING FOR BEYOND 2027?As the 2027 General Election.
COURT HALTS COAST WATER DISCONNECTIONS AS EJF CHALLENGES SH6 BILLION DEBT CLAIMKwale, 29 August 2026 —.
THE LEGENDARY 70-YEAR-OLD MZIMA PIPELINE LIVES TO BURST ANOTHER DAYGovernment Celebrates Repairing What It Failed.
TRAGIC LOSS OF JOHN KALAGHE JOSHUA LEAVES FAMILY AND COMMUNITY IN MOURNINGIt is with profound sorrow and.
THE NAIROBI–MOMBASA EXPRESSWAY: A DECADE OF PROMISES, YET NO HIGHWAY IN SIGHTThe Highway That Exists Only.
FROM FUEL TO DRINKING WATER: HOW A BILLION-SHILLING PIPELINE DREAM RAN AGROUNDA Lesson in Why Politics Should.
LIKONI BRIDGE: WHAT HAPPENED TO RUTO’S KSH 100 BILLION PROMISE?For years, residents of Mombasa and.
MZIMA PHASE TWO: SIX DECADES OF PROMISES, DELAYS AND GOVERNMENT FAILURECoast Residents Continue to Suffer as.
ABSENT LEADERSHIP OR CALCULATED DISRESPECT? QUESTIONS MOUNT OVER KINGI’S NO-SHOW AT MGANGE NYIKA FUNDRAISER.Serious questions are emerging following the.
ATHANAS MBELE’S “BIG 7 AGENDA” VISION POSITIONS WUNDANYI FOR TRANSFORMATIONAL GROWTHWundanyi is emerging at the center.
POLITICS ON OVERDRIVEKenya is not a permanent.
WHY TAITA TAVETA NEEDS ITS OWN POLITICAL VEHICLEBy Geoffrey Kimonge (GK) The Case.
HAS GREED CONSUMED THE TAITA TAVETA COUNTY ASSEMBLY?By Geoffrey Kimonge (GK) Has the.
THE COLLAPSE OF PAA: AMASON KINGI’S POLITICAL HOLLOWING EXPOSED IN MAGARINI AND TAITA TAVETABy any political measure, Pamoja.

Leave a Comment