“THIRST AND DECEIT: WHAT HAPPENED TO THE KSH 40 BILLION MZIMA PROJECT?”

 

Mzima Phase Two – Project Details & Timeline 

Origins & Scope 

The Mzima II project was conceived as a second pipeline from the Mzima Springs in the Tsavo‑West area, to supplement the existing Mzima I supply (started in 1953 and completed in 1957) and extend bulk water to arid regions of Taita‑Taveta County and to coastal counties (Mombasa, Kilifi, Kwale).

According to the Kenyan PPP portal, the project was structured as a 220 km pipeline and treatment/distribution works under a “30‑year term (3 years construction + 27 years operations)”.

Key Timeline Milestones  

  • July 17, 2017: The Coast Water Works Development Agency (CWWDA) signed an EPCF (Engineering, Procurement, Construction & Financing) contract worth US$335.34 million (~ KSh 36.7 billion) with Avic International Holding Corporation for Mzima II.
  • The public‐private partnership (PPP) model did not attract investors willing to take the risk at the cost quoted (~KSh 35 billion).
  • Some reports suggest that the scope and cost, plus the pipeline length (220 km) and treatment/distribution infrastructure, were too ambitious under the given economic environment.
  • Thus, the project was “frozen” or shelved in its original form while alternative approaches are considered.

Question of Local Revenue and Why TSAVO Area Funds Might Not Be Utilised for the Project  

– The region around Tsavo National Park (East & West) generates tourism and wildlife‐related revenues. Some of these often get remitted to national coffers rather than being locked into local reinvestment.

– It appears there is no publicly available, transparent breakdown showing how much revenue from Tsavo or the coastal water‐supply system has been earmarked or spent on Mzima II or Taita‑Taveta priority water supply needs.

– Because the government declared the project unviable and halted it (rather than shifted to an alternate model), funds that might have been mobilised (through PPP or national budget) remain dormant or reallocated.

– Local stakeholders argue: If the project is meant to benefit Taita‑Taveta (and help with water for both humans and wildlife, thus also reducing human‑wildlife conflict), the lack of direct reinvestment is a serious shortfall.

– Without transparent accountability or linking revenues from natural‑resource areas (like Tsavo tourism) to local infrastructure projects, there is a trust deficit between the community and the national government.

Summary & Implications  

– The Mzima II Project was ambitious and clearly needed: water‑scarce Taita‑Taveta County and parts of the coast would benefit.

– But the project timeline has significantly stalled: from contract signing (2017) to shelving (2024) with negligible site works and tiny budget allocations in recent years.

– The government’s reasoning centres on cost and investor reluctance — essentially saying the original model is not viable.

– For the local community, the key concerns are: why the promises made (including campaign promises of KSh 40 billion) have not materialised, and when will they receive tangible benefit?

– Without clear funding flows, transparent accountability, and alternative implementation models, the project remains in limbo — creating frustration, especially in Taita‑Taveta and among communities facing water shortages and wildlife conflicts.

Questions for Public Accountability 

1. What is the *updated business case* for Mzima II now that the original has been shelved? Has cost been re‑estimated?

2. How much funding (national, county, PPP) has already been spent on preparatory works (feasibility, ESIA, pipeline design) and what is its status?

3. Are revenues from Tsavo tourism or coastal water service levies ring‑fenced or accounted for in local water infrastructure budgets?

4. What timeline and budget is now being proposed for the water supply to Taita‑Taveta (via Mzima or alternate source) and when will operations commence?

Mwachere Shuma

Leave a Comment

View Comments

Share
Published by
Mwachere Shuma

Recent Posts

TAITA TAVETA: SEVEN DAYS HAVE ELAPSED — HAS SENATOR KAJWANG SENT WAKUJAA’S GOVERNMENT FILES TO EACC?

  By Kwaela News Network (KNN) | Governance & Accountability The seven-day ultimatum issued to…

17 hours ago

THE ERA OF POLITICAL EUPHORIA IN TAITA TAVETA COUNTY IS OVER

  The days when political party waves and symbolism single-handedly determined election outcomes in Taita-Taveta…

1 day ago

TAITA TAVETA: CAN THE DCI CRACK THE NUT? DORCAS MLGHU’S PUBLIC OUTBURST PUTS COUNTY EXECUTIVE UNDER FRESH PRESSURE

  The growing controversy surrounding the financial management of Taita Taveta County has taken another…

2 days ago

THE GOVERNOR DISCOVERS FISCAL DISCIPLINE — FOUR YEARS TOO LATE?

  Perhaps one of the most ironic moments of Governor Andrew Mwadime's appearance before the…

3 days ago

NDARA B LAND DISPUTE: 63 RESIDENTS SERVED WITH THREE-MONTH EVICTION NOTICE FOLLOWING COURT RULING

Affected families in Mlambenyi, Golani and Mto Mwagodi face a February 2027 deadline as the…

3 days ago

THE WRONG TIME: GOVERNOR WAKUJAA’S DEFENCE

During a Senate Public Finance Committee meeting, Taita Taveta Governor Andrew Mwadime, popularly known as…

5 days ago