Taita Taveta millions go to waste in stalled mega-projects

A past chaotic session in the Taita Taveta County Assembly. A task force has accused former administration of commissioning white elephant projects

By Renson Mnyamwezi

A task force report has unearthed massive wastage of funds on projects that were never completed.

The probe, ordered by Governor Granton Samboja, faulted officials of the former administration for investing millions of shillings in scattered projects across the county that have since stalled.

According to the report, some of the projects stalled midway even after money was allocated for them; others are complete but have never been put to use while others were abandoned by contractors for lack of payment.

“The projects were carried out in blatant disregard of technical advice on budgetary allocation, exclusion of the county legal office in signing contracts,” said the report.

“Yet another failure was honouring of payment by the county government and non-adherence to the contractual agreement by the contractors,” said the probe team.

Contractor payments

The county now risks paying millions of shillings to contractors for unused or incomplete projects.

In one instance, several polytechnics and dispensaries were built but still lack equipment, personnel, learning materials, furniture and drugs.

“It is advisable to allocate funds to one mega-project in a ward until it is fully completed and operational before embarking on other projects,” said the report.

The probe team concluded that a number of projects implemented by the former administration through the Ward Equalisation Fund were not only for political expediency but also undermined the county’s planning and budgetary process.

Speaking at his office when the task force handed him the report on Monday, Mr Samboja declared that his administration would only pay pending bills that were factual, verifiable and legitimate.

A poorly done Footbridge in taita Taveta County

The governor warned contractors and technical officers who did not carry out their work according to specifications that they would be dealt with according to the law.

Samboja said failure by technical officers to supervise projects provided a loophole for unscrupulous contractors to exploit and rob the county.

Records seen by The Standard indicate that the county administration owes contractors more than Sh978.7 million in pending bills.

Samboja has questioned the figure, wondering why the bills were not paid when more than Sh5.4 billion was available in the county coffers.

Pending bills

The governor said when he took office last year, he was informed that the county’s pending bills stood at Sh724 million, and ordered an audit of all projects before the bills could be settled.

“With these discrepancies in mind, I hereby order an immediate verification of all invoices, local purchase orders and inspection of certification for payment from technical officers,” he said.

The report was presented by former permanent secretary Philemon Mwaisaka.

Kwaela News Network

Leave a Comment
Share
Published by
Kwaela News Network

Recent Posts

TAITA TAVETA: SEVEN DAYS HAVE ELAPSED — HAS SENATOR KAJWANG SENT WAKUJAA’S GOVERNMENT FILES TO EACC?

  By Kwaela News Network (KNN) | Governance & Accountability The seven-day ultimatum issued to…

17 hours ago

THE ERA OF POLITICAL EUPHORIA IN TAITA TAVETA COUNTY IS OVER

  The days when political party waves and symbolism single-handedly determined election outcomes in Taita-Taveta…

1 day ago

TAITA TAVETA: CAN THE DCI CRACK THE NUT? DORCAS MLGHU’S PUBLIC OUTBURST PUTS COUNTY EXECUTIVE UNDER FRESH PRESSURE

  The growing controversy surrounding the financial management of Taita Taveta County has taken another…

2 days ago

THE GOVERNOR DISCOVERS FISCAL DISCIPLINE — FOUR YEARS TOO LATE?

  Perhaps one of the most ironic moments of Governor Andrew Mwadime's appearance before the…

3 days ago

NDARA B LAND DISPUTE: 63 RESIDENTS SERVED WITH THREE-MONTH EVICTION NOTICE FOLLOWING COURT RULING

Affected families in Mlambenyi, Golani and Mto Mwagodi face a February 2027 deadline as the…

3 days ago

THE WRONG TIME: GOVERNOR WAKUJAA’S DEFENCE

During a Senate Public Finance Committee meeting, Taita Taveta Governor Andrew Mwadime, popularly known as…

6 days ago