SH 230 MILLION MALINDI UPGRADE STARTS DESPITE INPUT CONCERNS

By Alphonse Gari

The tourism resort of Malindi is getting an upgrade after a Sh230 million World Bank project began this week.

The project includes tarmacking the Barclays Bank-Mtangani Road, building a new drainage system and building a recycling plant at the Malindi dumpsite.

The road works have started, paving 800 metres to bitumen standards. It was supposed to take six months but the contractor has promised to complete it in four months, the project manager said.

Some stakeholders complained there was no public participation, citing the change from attractive cabro to less costly bitumen.

A letter seen by the Star written by the Malindi Progressive Welfare Association demanded a copy of the board minutes concerning the type of road planned, the initial budget and all relevant information.

The letter signed by Kate Mwilkali and addressed to the Malindi Municipal Board chairman Aliasgar Kassamjee said they wrote to the CEC for Roads to be furnished information.

Engineer Hatmi Nurein, who is in charge of the road project, said they designed the road for bitumen tarmacking for Sh67 million.

”I know there is the drainage issue and I am going to take care of it with two cross culverts, one 900mm and the other 600mm,” he said.

Nurein said the project will  be ready by early November.

Malindi town Manager Silas Ngundo said the project was a big breakthrough for many businesses along the road.

During the rains, stormwater floods a section of the road, inconveniencing residents and visitors. The Paradise Hotel and Surahi Restaurant are seriously affected.

”Many visitors do not go to hotels because of the flooding but the project will change business for the better,” Nurein said.

Apart from restaurants, hotels and hospitals, the area has many residents who work in town where more business opportunities will open because of the new road.

The Kenya National Chamber of Commerce and Industry and the Malindi business community approved the project, calling it transformative.

Majid Swaleh, the chairman of KNCCI Kilifi county, said the project is popular because it connects the central area, Mtangani route and Ganda Road.

“Once it is tarmacked, new businesses will come up,” he said.

Majid said some stakeholders complained about the way the carpeting was changed from cabro to bitum without clear public participation.

The owner of Premier Guest House and Cottages in Malindi who also owns a hotel along the road said the key problem is drainage.

”We have suffered for too long. Guests’ vehicles used to get dirty driving along flooded roads,” he said.

~ The Star

Kwaela News Network

Leave a Comment
Share
Published by
Kwaela News Network

Recent Posts

TAITA TAVETA: SEVEN DAYS HAVE ELAPSED — HAS SENATOR KAJWANG SENT WAKUJAA’S GOVERNMENT FILES TO EACC?

  By Kwaela News Network (KNN) | Governance & Accountability The seven-day ultimatum issued to…

17 hours ago

THE ERA OF POLITICAL EUPHORIA IN TAITA TAVETA COUNTY IS OVER

  The days when political party waves and symbolism single-handedly determined election outcomes in Taita-Taveta…

1 day ago

TAITA TAVETA: CAN THE DCI CRACK THE NUT? DORCAS MLGHU’S PUBLIC OUTBURST PUTS COUNTY EXECUTIVE UNDER FRESH PRESSURE

  The growing controversy surrounding the financial management of Taita Taveta County has taken another…

2 days ago

THE GOVERNOR DISCOVERS FISCAL DISCIPLINE — FOUR YEARS TOO LATE?

  Perhaps one of the most ironic moments of Governor Andrew Mwadime's appearance before the…

3 days ago

NDARA B LAND DISPUTE: 63 RESIDENTS SERVED WITH THREE-MONTH EVICTION NOTICE FOLLOWING COURT RULING

Affected families in Mlambenyi, Golani and Mto Mwagodi face a February 2027 deadline as the…

3 days ago

THE WRONG TIME: GOVERNOR WAKUJAA’S DEFENCE

During a Senate Public Finance Committee meeting, Taita Taveta Governor Andrew Mwadime, popularly known as…

6 days ago