BAHARINI LAND ROW: LAMU MCAS SLAM THE BRAKES ON SH21 WIND POWER PLAN

By KALUME KAZUNGU
Plans to construct a Sh21 billion wind power plant in Lamu County have been dealt a huge blow after assembly members on Wednesday unanimously passed a motion to nullify the project over alleged failure to meet the required conditions.

The project was being undertaken by Baharini Wind Power, a partnership between Elicio Company from Belgium and Kenwind Holdings Ltd, a local firm.

A total of 3,206 acres of land had already been set aside for the project in Baharini, Lamu West. The project was expected to generate 90 megawatts of electricity upon completion.

While moving the motion, Bahari Ward MCA, Mr Anthony Njomo noted that the assembly had on July 22, 2015 resolved to approve the project on condition that all the required recommendations are met.

Among the conditions was that the project was not to use any other land set aside for other purposes.

LAND ALLOCATION

On Wednesday, Mr Njomo said Kenwind Power Project had failed to comply with some of the listed conditions, which led to confusion, displacement and chaos in the local community.

He said the land on which the investor intends to resettle those affected by the project had already been demarcated, surveyed and titled and there was no free land for resettlement.

The rep also noted that the investor was directly involved in the resettlement, instead of contracting SGS Kenya to work independently, hence directly affecting and influencing the outcome of the entire process.

NULLIFY PROJECT

“I, therefore, urge this house to nullify the project … and compel the county government to reallocate to the people affected the land that was meant for the project,” said Mr Njomo.

The investor had already launched a resettlement action plan last December.

In February, Kenya Power signed a 20-year Power Purchase Agreement with the firm.

There were plans to put up 38 turbines of 90MW capacity in Baharini village, about 40kms from the Lamu Port South Sudan Ethiopia Transport (Lapsset) Corridor project in Kililana.

~ Nation Media Group

Kwaela News Network

Leave a Comment
Share
Published by
Kwaela News Network

Recent Posts

TAITA TAVETA: SEVEN DAYS HAVE ELAPSED — HAS SENATOR KAJWANG SENT WAKUJAA’S GOVERNMENT FILES TO EACC?

  By Kwaela News Network (KNN) | Governance & Accountability The seven-day ultimatum issued to…

17 hours ago

THE ERA OF POLITICAL EUPHORIA IN TAITA TAVETA COUNTY IS OVER

  The days when political party waves and symbolism single-handedly determined election outcomes in Taita-Taveta…

1 day ago

TAITA TAVETA: CAN THE DCI CRACK THE NUT? DORCAS MLGHU’S PUBLIC OUTBURST PUTS COUNTY EXECUTIVE UNDER FRESH PRESSURE

  The growing controversy surrounding the financial management of Taita Taveta County has taken another…

2 days ago

THE GOVERNOR DISCOVERS FISCAL DISCIPLINE — FOUR YEARS TOO LATE?

  Perhaps one of the most ironic moments of Governor Andrew Mwadime's appearance before the…

3 days ago

NDARA B LAND DISPUTE: 63 RESIDENTS SERVED WITH THREE-MONTH EVICTION NOTICE FOLLOWING COURT RULING

Affected families in Mlambenyi, Golani and Mto Mwagodi face a February 2027 deadline as the…

3 days ago

THE WRONG TIME: GOVERNOR WAKUJAA’S DEFENCE

During a Senate Public Finance Committee meeting, Taita Taveta Governor Andrew Mwadime, popularly known as…

6 days ago